Over 1,200 Meters a Month at Bheri Babai: TBM Excavation in Himalayan Geology
Nepal's first TBM-driven tunnel was a success by any standard: The Robbins Double Shield machine bored up to 1,200 meters a month and finished the Bheri Babai Diversion Multipurpose Project nearly a year early. But how were crews able to bore so quickly? Why was this project built in a remote area of Nepal? And what made the contractor and owner ultimately decide to use a TBM for the first time?

Listen in on our conversation with Brad Grothen P.E., Robbins Technical Director, and Missy Isaman P.E., Robbins Project Engineer, as we discuss the challenges, lessons learned, and recommendations for future tunnels in mountainous geology. In this complimentary, 30-minute webinar we'll cover these topics and more. Join us for a live Q&A session at the end to get a thorough answer from our expert speakers.

Aug 13, 2020 08:00 AM in Pacific Time (US and Canada)

Webinar logo
* Required information
Loading

Speakers

Brad Grothen, P.E.
Technical Director @The Robbins Company
Brad Grothen, P.E. has a Bachelor of Science in Mechanical Engineering with an emphasis in Design and Manufacturing and a minor in Material Science Engineering from Washington State University. Grothen is based in Robbins’ Kent, Washington office and has specialized in custom industrial and construction equipment for over 20 years in a variety of roles, including mechanical and electrical design and project management. In his time at Robbins he has worked as a Sr. Design Engineer, Project Engineer, Engineering Manager, and most recently as Director of Engineering. Grothen is now Robbins Technical Director, leading overall product design and working directly with clients to present designs as well as develop concepts.
Missy Isaman, P.E.
Project Engineer @The Robbins Company
Missy Isaman has worked for The Robbins Company since 2010. Isaman earned her Bachelor of Science degree from Gonzaga University in 2002 and in 2010 she also earned her Professional Engineer’s license in Washington State. While at The Robbins Company, she has designed the backup systems for the Singapore Metro, Stillwater Mine (USA), Rossaga HEPP (Norway) and Baku Metro (Azerbaijan) tunnels, among others. Also, she has been the lead project engineer on projects such as the Liaoning T9 (China), Moscow Metro 2 and 4 (Russia) and the Gerede Water Transmission (Turkey) tunnels.